Yes indeed I try go deeper in the product and I suppose
the problem I am facing with is not new.
I found a VB script that works fine. It creates a new
project and present the holidays per ressource as tasks.
this is enough for me at the moment but I would like to
see it in the same Gantt chart
Thanks anyway, I will go and visit your site.
For those who are interessed I post here beneath the code
I found (the code has been written by Michael Magan,
thanks to him).
Sub HolidayGantt()
' Creates a new project, with a task for each resource
' The task bar shows the holidays for each resource
' The range for the calendar is from project start to 3
months beyond
' the project finish
' For the visual effect, we put a block at the start and
the end of the
' bar
' 14-Jun-2001 Michael Magan
Dim PrjSrc As Project ' Source project
Dim PrjDest As Project ' New (destination) project
Dim T As Task
Dim D As Date
Dim DCalStart As Date
Dim DCalEnd As Date
Set PrjSrc = ActiveProject
FileNew
Set PrjDest = ActiveProject
PrjDest.ProjectStart = PrjSrc.ProjectStart
' Set the date range for the holiday calendar
DCalStart = PrjSrc.ProjectStart
DCalEnd = PrjSrc.ProjectFinish + 90
For Each R In PrjSrc.Resources
Set T = PrjDest.Tasks.Add(Name:=R.Name)
' Set a dummy holiday at the start and end of the
calendar
' This creates a dotted line for the duration of this
task
T.TimeScaleData(DCalStart _
, DCalStart + 1 _
, pjTaskTimescaledWork _
, pjTimescaleDays)(1).Value = 8 * 60
T.TimeScaleData(DCalEnd _
, DCalEnd + 1 _
, pjTaskTimescaledWork _
, pjTimescaleDays)(1).Value = 8 * 60
' For each day of the project, compare the resource
calendar
' with the standard calendar. If the standard
calendar has
' a working day, and the resource calendar does not,
then it
' is a holiday
For D = DCalStart To DCalEnd
If PrjSrc.BaseCalendars(1).Period(D, D).Working And
Not _
R.Calendar.Period(D, D).Working Then
T.TimeScaleData(D _
, D + 1 _
, pjTaskTimescaledWork _
, pjTimescaleDays)(1).Value = 8 * 60
End If
Next D
Next R
End Sub
C@ndido
>-----Original Message-----
>Hi Candido,
>
>Nice to hear from you again - starting to be a user hey
>I have an article on this on my website
>HTH
>
>--
>Jan De Messemaeker
>Microsoft Project Most Valuable Professional
>http://users.online.be/prom-ade/index.htm
>32-495-300 620
>"Candido Rodriguez" <(E-Mail Removed)>
schreef in bericht
>news:1c9ca01c452c2$5fb92a00$(E-Mail Removed)...
>> MSP takes care of the holidays of a resource when
drawing
>> the bar in the GANT chart.
>> Is it possible to see the bar in a way holidays are
>> displayed differently than working days ?
>> Thanks for you answer.
>>
>> C@ndido
>>
>
>
>
>.
>