how do I use calender days instead of work days in project

J

Jim Aksel

Express durations as elapsed time. For example, you can say a task lasts 5d
and project interprets that as "5 work days". If you say 5ed this is elapsed
days or calendar days. It works with all the units of time, although some
make more sense than others.
 
D

Darrell

I would just create a seven day calendar and make every day a work day.

Tools/Change Work Times.../New.../Enter Name (Seven Day) /select make a copy
of Standard/Click OK/Click and Drag across Day header (S,M,T,W,T,F,S) to
highlight/select Nondefault Working time, set hours.

Project/Project Information.../Calendar/select Seven Day
 