Have found the gif file to be not that good at showing the whole chart. I
revert to printing the schedule to a PDF file then inserting that into the
document.
Is there a way to limit the timescale? When the conversation to a PDF i
done it puts the time scale up for the whole project (59 wks). The task
I am trying to show is for 29 week
One other question. I prefer to have the dates show as work weeks. Th
problem is for 2009 the calendar is showing 53 weeks but my company onl
has 52 weeks. Is there any way to adjust the standard calendar to sto
at 52 for 2009?
Thanks.
Rus