MS Project 2003 Web Access is removing/deleting task on its own

J

jstratton

Running a single server environment w/ web access -- approx 150 users.
Approx 2-3 times a week, a task (usually under the Admin Project section)
will disappear from the Web Access, but not the original Project file.
Resources must be reassigned to the Project/Task in order to resolve-- in
many cases, the task must be deleted and hours re-keyed. Any help
appreciated.
 