Need help to in MS Project Report, in my case, The current, Resource Hours Worked report, shows in H

M

mukulbhind

Hi All,
I Need help to in MS Project Report, in my case, The current, Resource
Hours Worked report, shows in Hours only for each resource.These hours
needs to be converted into days for easy calculation. how can i do
this?
Can anyone help me.
It much appreciate..
 
J

John

mukulbhind said:
Hi All,
I Need help to in MS Project Report, in my case, The current, Resource
Hours Worked report, shows in Hours only for each resource.These hours
needs to be converted into days for easy calculation. how can i do
this?
Can anyone help me.
It much appreciate..

mukulbhind,
You don't say which version of Project you are using so I'm not real
sure which report you are referring to. However, the "dimension" used to
show resource work is controlled by Tools/Options/Schedule tab, the
"work is entered in" selection box. Set it for "days" and you should get
what you want.

John
Project MVP
 
M

mukulbhind

Hi John,
Thanks for such information, as you have written that you
don't have clear which version i m using so i would like to tell you I
am using MS Project Professional 2003(11.2.2005.1801.15)SP2 and i also
trying to do which you have suggest me and i've another query is here,
in MS Project Report, The current Resource Hours Worked report shows
the cumulative Hours for all resources,But I would like to see the
totals for each resources when I generate for all resources. how can i
do this.
any idea very helpful for me..
Thanks,
Mukul
 
J

John

mukulbhind said:
Hi John,
Thanks for such information, as you have written that you
don't have clear which version i m using so i would like to tell you I
am using MS Project Professional 2003(11.2.2005.1801.15)SP2 and i also
trying to do which you have suggest me and i've another query is here,
in MS Project Report, The current Resource Hours Worked report shows
the cumulative Hours for all resources,But I would like to see the
totals for each resources when I generate for all resources. how can i
do this.
any idea very helpful for me..
Thanks,
Mukul

Mukul,
You're welcome. It wasn't necessary to make a separate post on your
other question. Nonetheless, I answered that one separately.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top