Rounding days in Project

 
 
peter
Guest
Posts: n/a
 
      10-24-2003, 02:00 AM
Hi,

Does anyone know how to stop the following occuring in
Microsoft Project (98);

When I enter a new task of 1 day and a start date of
23/03/04 then project defaults an end date of 24/03/04,
which to me indicates a 2 day task.

If I change the finish date to 23/03/04 the project then
changes the duration from 1 day to 0.88 days.

Thanks in advance.

 
Reply With Quote
 
 
 
 
Jan De Messemaeker
Guest
Posts: n/a
 
      10-24-2003, 07:25 AM
Hi Peter,

Please visit http://www.mvps.org/project/faqs.htm
Faq 5. Default Working Hours

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
"peter" <(E-Mail Removed)> schreef in bericht
news:046901c399d2$a1c59bd0$(E-Mail Removed)...
> Hi,
>
> Does anyone know how to stop the following occuring in
> Microsoft Project (98);
>
> When I enter a new task of 1 day and a start date of
> 23/03/04 then project defaults an end date of 24/03/04,
> which to me indicates a 2 day task.
>
> If I change the finish date to 23/03/04 the project then
> changes the duration from 1 day to 0.88 days.
>
> Thanks in advance.
>



 
Reply With Quote
 
Sarah
Guest
Posts: n/a
 
      10-24-2003, 11:53 AM
Peter,

It has to do with the actual time that the task starts and ends. I
would suggest changing the dates to a format that also shows time, and
this may help you to understand what it's doing. Also, if you have any
successors to that task, they should indicate a start date of
24/03/04, which is logical as they cannot start until the morning
after a one-day task ends. So there really isn't any problem with the
predecessor task showing a start date of 24/03/04. I know others have
answered similar questions here and could probably explain this
better. Any takers?

Sarah
 
Reply With Quote
 
Guest
Posts: n/a
 
      10-25-2003, 03:23 AM
Thanks Sarah / Jan,

You've helped me sort this out.

Peter
>-----Original Message-----
>Hi,
>
>Does anyone know how to stop the following occuring in
>Microsoft Project (98);
>
>When I enter a new task of 1 day and a start date of
>23/03/04 then project defaults an end date of 24/03/04,
>which to me indicates a 2 day task.
>
>If I change the finish date to 23/03/04 the project then
>changes the duration from 1 day to 0.88 days.
>
>Thanks in advance.
>
>.
>

 
Reply With Quote
 
 
 
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
probability that project will we finished two days before planed dayin project talar Project General 4 12-10-2009 05:35 PM
Network days rounding off hours Thomas T Excel Misc 7 03-31-2008 12:53 PM
Stop rounding Hours into days bungy A/C Access Reports 7 11-09-2006 06:08 PM
how do I use calender days instead of work days in project Mike Project General 2 07-19-2006 10:33 PM
Leave days or sick days for individuals in project Glenn H Project General 3 05-28-2004 02:54 PM



All times are GMT. The time now is 10:44 AM.
Microsoft Office Forums is not affiliated with Microsoft Corporation.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115