L
LS123
Hi,
I have made a very big programme (approx. 3000 activities) & circulated it
to all the stakeholders of the project including the construction team. Due
to uncertain nature of the project I need to revise the programme on monthly
basis. Every month there are significant addition, deletion & logic changes
of the activities.
In doing so, the ID column of a particular activity keeps on changing on
every deletion/addition of activities. During the meetings It was difficult
to refer activities from current & previous versions as the ID kept on
changing.
Then I applied a Text col. to have a Static ID for all activities.
Now, to discuss the logic during the meetings I want to show the
predeccessors & successors on the Gnatt BARS in terms of the Static ID!!!
Like - 1123C FS+5days
I know there is a field called "unique ID" for the same, but using this to
find out the predecesors & Successors on several A0 printouts of the
programme is really clumsy for a big programme, especially when you have got
28 revisions to your programme!!!
Is there a way to do this?
Any relevent views will be appreciated.
I have made a very big programme (approx. 3000 activities) & circulated it
to all the stakeholders of the project including the construction team. Due
to uncertain nature of the project I need to revise the programme on monthly
basis. Every month there are significant addition, deletion & logic changes
of the activities.
In doing so, the ID column of a particular activity keeps on changing on
every deletion/addition of activities. During the meetings It was difficult
to refer activities from current & previous versions as the ID kept on
changing.
Then I applied a Text col. to have a Static ID for all activities.
Now, to discuss the logic during the meetings I want to show the
predeccessors & successors on the Gnatt BARS in terms of the Static ID!!!
Like - 1123C FS+5days
I know there is a field called "unique ID" for the same, but using this to
find out the predecesors & Successors on several A0 printouts of the
programme is really clumsy for a big programme, especially when you have got
28 revisions to your programme!!!
Is there a way to do this?
Any relevent views will be appreciated.