Displaying Resource Initial in Gantt Chart

M

Mark

Hi - Is there a way to display the resource names as resource initials
in the Gantt Chart view? Thanks in advance. Mark.
 
D

Dale Howard [MVP]

Mark --

Assuming you have filled in the Initials column for each resource in your
Resource Sheet view of the project, do the following to show the initials at
the end of each Gantt bar in the Gantt Chart view:

1. Open the project in question
2. Click Format - Bar Styles
3. In the Bar Styles dialog, click the Text tab
4. Click the drop-down list the Right text and select "Resource Initials"
5. Click OK

Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top