Assuming you have filled in the Initials column for each resource in your
Resource Sheet view of the project, do the following to show the initials at
the end of each Gantt bar in the Gantt Chart view:
1. Open the project in question
2. Click Format - Bar Styles
3. In the Bar Styles dialog, click the Text tab
4. Click the drop-down list the Right text and select "Resource Initials"
5. Click OK
Hope this helps.