corina said:
I need to create a time-phased budget in MS project, but I have no idea where
to start. Any suggestions??
Thank you,
corina,
Some might say that the Baseline Cost field is the budget but it kind of
depends on how you view a "budget".
I suggest you set up your plan complete with resources. The original
estimated cost will be the Cost field and this would be treated as the
budget. When it is all set up, go to Tools/Tracking/Save Baseline and
save a baseline for the entire project. Project then captures all the
data in the Cost field and saves it in the Baseline Cost field so it can
be used for earned value calculations or any other comparative analysis.
Hope this helps.
John
Project MVP