How do I switch MSProject from Baseline to Baseline 1?

A

Albert@CSC

I can save multiple baselines but MSProject always computes schedule and
other variances from 'Baseline'. How do I switch to compute from 'Baseline 1'?
 
G

Gérard Ducouret

Hello Albert,

Tools / options / Calculation / Earned Value : Baseline for Earned value
calculations

Gérard Ducouret