D
Dmitry
Hello,
I put several project plans on one page. However, some of tasks were
rescheduled for later because all the tasks have As Late As Possible
constraints. Now I have slacks that I cannot get rid of. Looks like Project
combined all plans into a "single" plan and moves all possible tasks further
in time to the last possible date from ANY of the project plans. For example,
of two projects the first one (A) finishes in 3 months, the second one (B) -
in 1 month. Project A made the project B start as late as possible (not when
it is supposed to start). After I set a start date for the first task of the
project B I still have a slack between the 1st and 2nd tasks of the project
B. Both of the projects finish in 3 months.
How can I make Microsoft Project treat plans as separate ones on one page?
Thanks a lot in advance,
Dmitry
I put several project plans on one page. However, some of tasks were
rescheduled for later because all the tasks have As Late As Possible
constraints. Now I have slacks that I cannot get rid of. Looks like Project
combined all plans into a "single" plan and moves all possible tasks further
in time to the last possible date from ANY of the project plans. For example,
of two projects the first one (A) finishes in 3 months, the second one (B) -
in 1 month. Project A made the project B start as late as possible (not when
it is supposed to start). After I set a start date for the first task of the
project B I still have a slack between the 1st and 2nd tasks of the project
B. Both of the projects finish in 3 months.
How can I make Microsoft Project treat plans as separate ones on one page?
Thanks a lot in advance,
Dmitry