Level resources effect % allocation

C

carmitpl

I have resource that is allocated in 50% to specific task. The task is
20% work completed.
After leveling, the % allocation is become 100%/
Any advice?
 
G

Gérard Ducouret

Hello,

The leveling feature will *never* change the % of a resource allocation on
a task
May be the resource entered an Actual Work of 8h on one day. So now Project
displays an allocation of 100%

Hope this helps,

Gérard Ducouret
 