MSP levels actuals to a time period

E

Erkki Piipari

Greetings.

I wonder, if anybody could give a hint in the following
case :
- The resource keys-in 15 hours for 29.12.03 and 20.12.03
(WA)
- The PM updates actuals as is
- MSP2002 calculates the actuals to the plan: 0,53 hours
for each day, starting from 29.12.03 and ending to 6.02.04

Previous actuals are correctly in the plan - why this
sudden change. I can not find any project level -
parameters to achieve this and enterprise settings have
not been touched. What about task- or assignment level ?
Can field values (contour...) affect this.

PS The only way I could reproduce this problem was to give
the assignment an actual finish date in the future. The PM
in question says she has not done so.

Thanks in advance.

Erkki
 
G

Gary L. Chefetz [MVP]

You can reproduce this behavior by creating a fixed duration task with a
duration that long as well. One would have to see the plan to venture a
guess here.
 