E
Erkki Piipari
Greetings.
I wonder, if anybody could give a hint in the following
case :
- The resource keys-in 15 hours for 29.12.03 and 20.12.03
(WA)
- The PM updates actuals as is
- MSP2002 calculates the actuals to the plan: 0,53 hours
for each day, starting from 29.12.03 and ending to 6.02.04
Previous actuals are correctly in the plan - why this
sudden change. I can not find any project level -
parameters to achieve this and enterprise settings have
not been touched. What about task- or assignment level ?
Can field values (contour...) affect this.
PS The only way I could reproduce this problem was to give
the assignment an actual finish date in the future. The PM
in question says she has not done so.
Thanks in advance.
Erkki
I wonder, if anybody could give a hint in the following
case :
- The resource keys-in 15 hours for 29.12.03 and 20.12.03
(WA)
- The PM updates actuals as is
- MSP2002 calculates the actuals to the plan: 0,53 hours
for each day, starting from 29.12.03 and ending to 6.02.04
Previous actuals are correctly in the plan - why this
sudden change. I can not find any project level -
parameters to achieve this and enterprise settings have
not been touched. What about task- or assignment level ?
Can field values (contour...) affect this.
PS The only way I could reproduce this problem was to give
the assignment an actual finish date in the future. The PM
in question says she has not done so.
Thanks in advance.
Erkki