We use consolidated files to open groups of individual MS
Project files. We recently upgraded from 98 to 2002. We
opened and converted all of our individual files. We
then opened and converted the consolidated files. From a
consolidated file, I expand a specific file and go to a
specific summary task. The Start date and Actual Start
date do not match. I then close the consolidated and
open that file individually. The Start date and Actual
Start date are the same. Any ideas?