B
Brad
I'm using Project Professional 2003. I'm usually running anywhere from 4 to
8 projects at one time, all pulling from a Resource Pool that I created. I
would like to be able to run a report across projects, which would provide me
w/ Work, Actual Work, and Remaining Work. I would like to be able to run
this report per resource, per resource group, or per project, but I have been
unsuccessful thus far in figuring this out. Could someone point me in the
right direction?
Thanks,
Brad
8 projects at one time, all pulling from a Resource Pool that I created. I
would like to be able to run a report across projects, which would provide me
w/ Work, Actual Work, and Remaining Work. I would like to be able to run
this report per resource, per resource group, or per project, but I have been
unsuccessful thus far in figuring this out. Could someone point me in the
right direction?
Thanks,
Brad