Hi Mike,
Thank you for your reply!
I am using MS Project 2003 Standard. I am working with a Master schedule,
i.e. I have several schedules consolidated into one. I am trying to set a
baseline for a huge initiative that has already begun (several tasks are
partially complete). There is a change initiative project team that will be
monitoring all the sub-projects and reporting to the executives.
I used mouse clicks, that is I went to Tools/Tracking/Save Baseline... I
saved baseline under "Baseline" since it was my first time saving the
baseline. The "For:" option was set to "Entire Project."
Then I clicked OK.
Then in the entry table I inserted the column "Baseline Start" and "Baseline
Duration." The only data viewable in these columns is "NA" in all cells
except for at the summary task level. Are the lowest level tasks not
baselined? Also, when I look at the gantt bars in the Tracking Gantt view, I
do not see the the baseline bar next to the task bar, even for the summary
tasks that do have some data saved.
Am I missing something? Am I expecting something that won't be available?
Thanks,
Melanie