A
Arnie
Scenario:
Task: Build Shed
Duration: 80hours
Task Type: Fixed Duration, Not effort Driven
Task Calendar: Shed
Resource: Gus
Resource Calendar: Shed
Std. Rate: $10.00/hour
Ovt. Rate: $15.00/hour
Project Start Date: 11/07/2005
Project Calendar: Shed
Shed Calendar:
11/07/2005 - 11/11/2005 8:00am - 12:00pm -1:00pm - 5:00pm
11/14/2005 - 11/18/2005 7:00am - 12:00pm -1:00pm - 6:00pm
Options:
Default Start: 8:00am
Default end : 5:00pm
Hours per day: 8
Hours per week: 40
Days per month: 20
Problem:
The Gantt chart correctly shows that the task starts on 11/7/2005 and
ends on 11/17/2005 (9 days), with a duration of 80 hours. The summary
task and calendar indicate that the task takes 10 days. Is this
discrepancy normal or am I missing something?
Task: Build Shed
Duration: 80hours
Task Type: Fixed Duration, Not effort Driven
Task Calendar: Shed
Resource: Gus
Resource Calendar: Shed
Std. Rate: $10.00/hour
Ovt. Rate: $15.00/hour
Project Start Date: 11/07/2005
Project Calendar: Shed
Shed Calendar:
11/07/2005 - 11/11/2005 8:00am - 12:00pm -1:00pm - 5:00pm
11/14/2005 - 11/18/2005 7:00am - 12:00pm -1:00pm - 6:00pm
Options:
Default Start: 8:00am
Default end : 5:00pm
Hours per day: 8
Hours per week: 40
Days per month: 20
Problem:
The Gantt chart correctly shows that the task starts on 11/7/2005 and
ends on 11/17/2005 (9 days), with a duration of 80 hours. The summary
task and calendar indicate that the task takes 10 days. Is this
discrepancy normal or am I missing something?