Task Usage and Resource Usage Reports

L

LindaJ

I am using Microsoft Project 2003. In my project I have run both the
Resource Usage and Task Usage Reports selecting tasks for the rows and work
for the columns, filtering with using resource....
In the Details tab I opted for both row and column totals. What do the
column and row totals on the report represent? I summed the work values for
each column and row on an adding machine and the values shown do not sum to
the row and column totals on the report.

Thanks so much, in advance, for your assistance.
Linda
 
J

JulieS

Hi Linda,

My comments are inline.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


LindaJ said:
I am using Microsoft Project 2003. In my project I have run both the
Resource Usage and Task Usage Reports selecting tasks for the rows and
work
for the columns, filtering with using resource....
In the Details tab I opted for both row and column totals. What do
the
column and row totals on the report represent?

[Julie] The row totals in the Task Usage view show the total work for
the Task throughout the entire project. If you add the work total for
each day or week (represented by the columns in the report) across
horizontally, it should equal the row total. The Column totals
represent the total work for all assignments for the day or week
(represented by the columns in the report) -- essentially adding down
each column. The row totals in the Resource Usage view, equal the total
work for the Resource across all of his/her assignments in the project.
There are no column totals for the Resource Usage report.
I summed the work values for
each column and row on an adding machine and the values shown do not
sum to
the row and column totals on the report.

[Julie] I assume you are comparing the Task Usage Report to the Resource
Usage report and seeing a difference. If you are comparing the two
reports and using the Using Resource Filter, I would expect to see
differences. The Using Resource Filter is a Task Filter and temporarily
filters out the Assignments for all resources other than the filtered
resource. So if you run the Task Usage Report and filter for the
Resource named Bob, you are only seeing the Tasks which Bob is assigned
to, and consequently the work values will only show Bob's work on those
tasks. If you run the Resource Usage report, you are seeing the work
values for *all* resources, not just Bob.
 
L

LindaJ

Thank you, JulieS! Yes, I do see differences between the reports. thank you
for explaining the results of the filter in each report.

The row totals do show the total work hours for the entire project,
horizontally and are summed correctly.

In the Task Usage Report showing all work assigned to 'Bob', the column
headings are my third level of the timescale, 'weeks'. The column (weeks)
totals do not sum correctly for 'Bob's' assignments. I thought it may also
be showing the total work hours assigned for every task for every resource
for that week, so I changed the filter to "All Tasks" and that report gave me
different coumn totals.

Can you tell me what the column total designated as weeks is?

Thanks!

JulieS said:
Hi Linda,

My comments are inline.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


LindaJ said:
I am using Microsoft Project 2003. In my project I have run both the
Resource Usage and Task Usage Reports selecting tasks for the rows and
work
for the columns, filtering with using resource....
In the Details tab I opted for both row and column totals. What do
the
column and row totals on the report represent?

[Julie] The row totals in the Task Usage view show the total work for
the Task throughout the entire project. If you add the work total for
each day or week (represented by the columns in the report) across
horizontally, it should equal the row total. The Column totals
represent the total work for all assignments for the day or week
(represented by the columns in the report) -- essentially adding down
each column. The row totals in the Resource Usage view, equal the total
work for the Resource across all of his/her assignments in the project.
There are no column totals for the Resource Usage report.
I summed the work values for
each column and row on an adding machine and the values shown do not
sum to
the row and column totals on the report.

[Julie] I assume you are comparing the Task Usage Report to the Resource
Usage report and seeing a difference. If you are comparing the two
reports and using the Using Resource Filter, I would expect to see
differences. The Using Resource Filter is a Task Filter and temporarily
filters out the Assignments for all resources other than the filtered
resource. So if you run the Task Usage Report and filter for the
Resource named Bob, you are only seeing the Tasks which Bob is assigned
to, and consequently the work values will only show Bob's work on those
tasks. If you run the Resource Usage report, you are seeing the work
values for *all* resources, not just Bob.
Thanks so much, in advance, for your assistance.
Linda
 
J

JulieS

Hi Linda,

You're most welcome and thanks for the feedback.

To your last question -- I assume you are trying to add the columns of
data vertically and the totals for the listed tasks are not adding
correctly at the bottom of the report.

I don't think this is an issue with weeks, but that the row column
totals *are* showing all work for all resources assigned to the task --
not just Bob's work. For example, I have a task with 2 resources
assigned, Bob and Sue. Bob is scheduled for 40 hours of work on the
task and Sue is scheduled for 40 hours of work. The task starts on 16
April and ends on 20 April. It falls into the week beginning April 15
and is the only task scheduled for that week. The column total shows 80
hours even though the only assignment visible is Bob's assignment for 40
hours. In the report, the top line is the task name line and the work
shows the total work on the task - 80 hours. Indented underneath the
task name line is Bob's name and the 40 hours for Bob appears. The
total at the bottom of the column is 80, the total work on the task not
120 hours as Bob's 40 hours are included in the 80. Does this describe
what you are seeing?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


LindaJ said:
Thank you, JulieS! Yes, I do see differences between the reports.
thank you
for explaining the results of the filter in each report.

The row totals do show the total work hours for the entire project,
horizontally and are summed correctly.

In the Task Usage Report showing all work assigned to 'Bob', the
column
headings are my third level of the timescale, 'weeks'. The column
(weeks)
totals do not sum correctly for 'Bob's' assignments. I thought it may
also
be showing the total work hours assigned for every task for every
resource
for that week, so I changed the filter to "All Tasks" and that report
gave me
different coumn totals.

Can you tell me what the column total designated as weeks is?

Thanks!

JulieS said:
Hi Linda,

My comments are inline.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project


LindaJ said:
I am using Microsoft Project 2003. In my project I have run both
the
Resource Usage and Task Usage Reports selecting tasks for the rows
and
work
for the columns, filtering with using resource....
In the Details tab I opted for both row and column totals. What do
the
column and row totals on the report represent?

[Julie] The row totals in the Task Usage view show the total work for
the Task throughout the entire project. If you add the work total
for
each day or week (represented by the columns in the report) across
horizontally, it should equal the row total. The Column totals
represent the total work for all assignments for the day or week
(represented by the columns in the report) -- essentially adding down
each column. The row totals in the Resource Usage view, equal the
total
work for the Resource across all of his/her assignments in the
project.
There are no column totals for the Resource Usage report.
I summed the work values for
each column and row on an adding machine and the values shown do
not
sum to
the row and column totals on the report.

[Julie] I assume you are comparing the Task Usage Report to the
Resource
Usage report and seeing a difference. If you are comparing the two
reports and using the Using Resource Filter, I would expect to see
differences. The Using Resource Filter is a Task Filter and
temporarily
filters out the Assignments for all resources other than the filtered
resource. So if you run the Task Usage Report and filter for the
Resource named Bob, you are only seeing the Tasks which Bob is
assigned
to, and consequently the work values will only show Bob's work on
those
tasks. If you run the Resource Usage report, you are seeing the work
values for *all* resources, not just Bob.
Thanks so much, in advance, for your assistance.
Linda
 
L

LindaJ

Yes, it does. Which report will give me the correct work hours by rows and
columns filtered by a specific resource? I have read through all the posts
regarding reports and I think the "Who does what" and the "Who Does What
When" Reports are the closest fit for my needs. But, I'm tired of guessing
and modifying reports, I would like your expert wisdom.

Thanks!
LindaJ


JulieS said:
Hi Linda,

You're most welcome and thanks for the feedback.

To your last question -- I assume you are trying to add the columns of
data vertically and the totals for the listed tasks are not adding
correctly at the bottom of the report.

I don't think this is an issue with weeks, but that the row column
totals *are* showing all work for all resources assigned to the task --
not just Bob's work. For example, I have a task with 2 resources
assigned, Bob and Sue. Bob is scheduled for 40 hours of work on the
task and Sue is scheduled for 40 hours of work. The task starts on 16
April and ends on 20 April. It falls into the week beginning April 15
and is the only task scheduled for that week. The column total shows 80
hours even though the only assignment visible is Bob's assignment for 40
hours. In the report, the top line is the task name line and the work
shows the total work on the task - 80 hours. Indented underneath the
task name line is Bob's name and the 40 hours for Bob appears. The
total at the bottom of the column is 80, the total work on the task not
120 hours as Bob's 40 hours are included in the 80. Does this describe
what you are seeing?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


LindaJ said:
Thank you, JulieS! Yes, I do see differences between the reports.
thank you
for explaining the results of the filter in each report.

The row totals do show the total work hours for the entire project,
horizontally and are summed correctly.

In the Task Usage Report showing all work assigned to 'Bob', the
column
headings are my third level of the timescale, 'weeks'. The column
(weeks)
totals do not sum correctly for 'Bob's' assignments. I thought it may
also
be showing the total work hours assigned for every task for every
resource
for that week, so I changed the filter to "All Tasks" and that report
gave me
different coumn totals.

Can you tell me what the column total designated as weeks is?

Thanks!

JulieS said:
Hi Linda,

My comments are inline.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project


I am using Microsoft Project 2003. In my project I have run both
the
Resource Usage and Task Usage Reports selecting tasks for the rows
and
work
for the columns, filtering with using resource....
In the Details tab I opted for both row and column totals. What do
the
column and row totals on the report represent?

[Julie] The row totals in the Task Usage view show the total work for
the Task throughout the entire project. If you add the work total
for
each day or week (represented by the columns in the report) across
horizontally, it should equal the row total. The Column totals
represent the total work for all assignments for the day or week
(represented by the columns in the report) -- essentially adding down
each column. The row totals in the Resource Usage view, equal the
total
work for the Resource across all of his/her assignments in the
project.
There are no column totals for the Resource Usage report.

I summed the work values for
each column and row on an adding machine and the values shown do
not
sum to
the row and column totals on the report.

[Julie] I assume you are comparing the Task Usage Report to the
Resource
Usage report and seeing a difference. If you are comparing the two
reports and using the Using Resource Filter, I would expect to see
differences. The Using Resource Filter is a Task Filter and
temporarily
filters out the Assignments for all resources other than the filtered
resource. So if you run the Task Usage Report and filter for the
Resource named Bob, you are only seeing the Tasks which Bob is
assigned
to, and consequently the work values will only show Bob's work on
those
tasks. If you run the Resource Usage report, you are seeing the work
values for *all* resources, not just Bob.


Thanks so much, in advance, for your assistance.
Linda
 
L

LindaJ

Hi JulieS,

I used the views and filters to show the information, then copied and pasted
it into Excel. I converted the work hours text to numbers so I can Sum them.
It worked.

Thank you so much for your assistance!

LindaJ said:
Yes, it does. Which report will give me the correct work hours by rows and
columns filtered by a specific resource? I have read through all the posts
regarding reports and I think the "Who does what" and the "Who Does What
When" Reports are the closest fit for my needs. But, I'm tired of guessing
and modifying reports, I would like your expert wisdom.

Thanks!
LindaJ


JulieS said:
Hi Linda,

You're most welcome and thanks for the feedback.

To your last question -- I assume you are trying to add the columns of
data vertically and the totals for the listed tasks are not adding
correctly at the bottom of the report.

I don't think this is an issue with weeks, but that the row column
totals *are* showing all work for all resources assigned to the task --
not just Bob's work. For example, I have a task with 2 resources
assigned, Bob and Sue. Bob is scheduled for 40 hours of work on the
task and Sue is scheduled for 40 hours of work. The task starts on 16
April and ends on 20 April. It falls into the week beginning April 15
and is the only task scheduled for that week. The column total shows 80
hours even though the only assignment visible is Bob's assignment for 40
hours. In the report, the top line is the task name line and the work
shows the total work on the task - 80 hours. Indented underneath the
task name line is Bob's name and the 40 hours for Bob appears. The
total at the bottom of the column is 80, the total work on the task not
120 hours as Bob's 40 hours are included in the 80. Does this describe
what you are seeing?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


LindaJ said:
Thank you, JulieS! Yes, I do see differences between the reports.
thank you
for explaining the results of the filter in each report.

The row totals do show the total work hours for the entire project,
horizontally and are summed correctly.

In the Task Usage Report showing all work assigned to 'Bob', the
column
headings are my third level of the timescale, 'weeks'. The column
(weeks)
totals do not sum correctly for 'Bob's' assignments. I thought it may
also
be showing the total work hours assigned for every task for every
resource
for that week, so I changed the filter to "All Tasks" and that report
gave me
different coumn totals.

Can you tell me what the column total designated as weeks is?

Thanks!

:

Hi Linda,

My comments are inline.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project


I am using Microsoft Project 2003. In my project I have run both
the
Resource Usage and Task Usage Reports selecting tasks for the rows
and
work
for the columns, filtering with using resource....
In the Details tab I opted for both row and column totals. What do
the
column and row totals on the report represent?

[Julie] The row totals in the Task Usage view show the total work for
the Task throughout the entire project. If you add the work total
for
each day or week (represented by the columns in the report) across
horizontally, it should equal the row total. The Column totals
represent the total work for all assignments for the day or week
(represented by the columns in the report) -- essentially adding down
each column. The row totals in the Resource Usage view, equal the
total
work for the Resource across all of his/her assignments in the
project.
There are no column totals for the Resource Usage report.

I summed the work values for
each column and row on an adding machine and the values shown do
not
sum to
the row and column totals on the report.

[Julie] I assume you are comparing the Task Usage Report to the
Resource
Usage report and seeing a difference. If you are comparing the two
reports and using the Using Resource Filter, I would expect to see
differences. The Using Resource Filter is a Task Filter and
temporarily
filters out the Assignments for all resources other than the filtered
resource. So if you run the Task Usage Report and filter for the
Resource named Bob, you are only seeing the Tasks which Bob is
assigned
to, and consequently the work values will only show Bob's work on
those
tasks. If you run the Resource Usage report, you are seeing the work
values for *all* resources, not just Bob.


Thanks so much, in advance, for your assistance.
Linda
 
J

JulieS

Hi Linda,

Sorry I couldn't get back to you earlier, but the good news is -- it
sounds like you have found a solution that works. Glad to know things
are better you're welcome for the assistance and thanks for the
feedback.

Be sure to visit again if you have any other questions.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project

LindaJ said:
Hi JulieS,

I used the views and filters to show the information, then copied and
pasted
it into Excel. I converted the work hours text to numbers so I can Sum
them.
It worked.

Thank you so much for your assistance!

LindaJ said:
Yes, it does. Which report will give me the correct work hours by
rows and
columns filtered by a specific resource? I have read through all the
posts
regarding reports and I think the "Who does what" and the "Who Does
What
When" Reports are the closest fit for my needs. But, I'm tired of
guessing
and modifying reports, I would like your expert wisdom.

Thanks!
LindaJ


JulieS said:
Hi Linda,

You're most welcome and thanks for the feedback.

To your last question -- I assume you are trying to add the columns
of
data vertically and the totals for the listed tasks are not adding
correctly at the bottom of the report.

I don't think this is an issue with weeks, but that the row column
totals *are* showing all work for all resources assigned to the
task --
not just Bob's work. For example, I have a task with 2 resources
assigned, Bob and Sue. Bob is scheduled for 40 hours of work on
the
task and Sue is scheduled for 40 hours of work. The task starts on
16
April and ends on 20 April. It falls into the week beginning April
15
and is the only task scheduled for that week. The column total
shows 80
hours even though the only assignment visible is Bob's assignment
for 40
hours. In the report, the top line is the task name line and the
work
shows the total work on the task - 80 hours. Indented underneath
the
task name line is Bob's name and the 40 hours for Bob appears. The
total at the bottom of the column is 80, the total work on the task
not
120 hours as Bob's 40 hours are included in the 80. Does this
describe
what you are seeing?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project


Thank you, JulieS! Yes, I do see differences between the
reports.
thank you
for explaining the results of the filter in each report.

The row totals do show the total work hours for the entire
project,
horizontally and are summed correctly.

In the Task Usage Report showing all work assigned to 'Bob', the
column
headings are my third level of the timescale, 'weeks'. The
column
(weeks)
totals do not sum correctly for 'Bob's' assignments. I thought
it may
also
be showing the total work hours assigned for every task for every
resource
for that week, so I changed the filter to "All Tasks" and that
report
gave me
different coumn totals.

Can you tell me what the column total designated as weeks is?

Thanks!

:

Hi Linda,

My comments are inline.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project


I am using Microsoft Project 2003. In my project I have run
both
the
Resource Usage and Task Usage Reports selecting tasks for the
rows
and
work
for the columns, filtering with using resource....
In the Details tab I opted for both row and column totals.
What do
the
column and row totals on the report represent?

[Julie] The row totals in the Task Usage view show the total
work for
the Task throughout the entire project. If you add the work
total
for
each day or week (represented by the columns in the report)
across
horizontally, it should equal the row total. The Column totals
represent the total work for all assignments for the day or week
(represented by the columns in the report) -- essentially adding
down
each column. The row totals in the Resource Usage view, equal
the
total
work for the Resource across all of his/her assignments in the
project.
There are no column totals for the Resource Usage report.

I summed the work values for
each column and row on an adding machine and the values shown
do
not
sum to
the row and column totals on the report.

[Julie] I assume you are comparing the Task Usage Report to the
Resource
Usage report and seeing a difference. If you are comparing the
two
reports and using the Using Resource Filter, I would expect to
see
differences. The Using Resource Filter is a Task Filter and
temporarily
filters out the Assignments for all resources other than the
filtered
resource. So if you run the Task Usage Report and filter for
the
Resource named Bob, you are only seeing the Tasks which Bob is
assigned
to, and consequently the work values will only show Bob's work
on
those
tasks. If you run the Resource Usage report, you are seeing the
work
values for *all* resources, not just Bob.


Thanks so much, in advance, for your assistance.
Linda
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top