M
Marissa
Hi,
I am learning Project and have a question....ok, several. But I will start
with this one.
I have added all of the tasks, milestones, etc. and am looking into the
Resource Usage and my resources are over allocated. However, that is not my
problem, my probelm is that the hours for work that has passed is appearring
and is being counted as work that has to be completed. However, it has been
completed and I dont think that it should be appearring or be counted against
my hours that are remaining. How do i fix this?
Marissa
I am learning Project and have a question....ok, several. But I will start
with this one.
I have added all of the tasks, milestones, etc. and am looking into the
Resource Usage and my resources are over allocated. However, that is not my
problem, my probelm is that the hours for work that has passed is appearring
and is being counted as work that has to be completed. However, it has been
completed and I dont think that it should be appearring or be counted against
my hours that are remaining. How do i fix this?
Marissa