W
wendyB
Hi
I have filters and formulae that point to the "Baseline Start" and "Baseline
Finish" fields. I also keep multiple levels of baseline information. The
latest version will always be the next available Baseline number. Doesn't
Project automatically transfer old baseline to the next incremented baseline
number?
The only workaround I can think of: Save baseline twice each time, once in
"Baseline", and then again starting from the largest Baseline number,
Baseline 10. The next time replace "Baseline" with the latest baseline info,
and save that as Baseline 9, and so on.
Thanks
Wendy
I have filters and formulae that point to the "Baseline Start" and "Baseline
Finish" fields. I also keep multiple levels of baseline information. The
latest version will always be the next available Baseline number. Doesn't
Project automatically transfer old baseline to the next incremented baseline
number?
The only workaround I can think of: Save baseline twice each time, once in
"Baseline", and then again starting from the largest Baseline number,
Baseline 10. The next time replace "Baseline" with the latest baseline info,
and save that as Baseline 9, and so on.
Thanks
Wendy