Track Expenses

 
 
Diane
Guest
Posts: n/a
 
      05-16-2005, 08:11 PM
Is there/What is the best way to track expenses in Project Pro/Project Server?

I am planning on exporting data out of Project into my financial package &
would love to suck any expenses (parking, food, lodging, etc) one might occur
on a project as well as the hours spent.

Thank you.

Regards,
Diane
 
Reply With Quote
 
 
 
 
Steve House [Project MVP]
Guest
Posts: n/a
 
      05-16-2005, 09:49 PM
Some of theose expenses can be entered as fixed costs while others like per
diem might better be tracked as material resources. If you drive to a site
and are there 3 days you might show a fixed cost of $120 ($20 parking plus
$100 gas) while there's a 3 day assignment of the per diem that is shown in
the resource sheet as a material resource with a $75 per day standard rate.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"Diane" <(E-Mail Removed)> wrote in message
news:FC7236B6-4E69-4904-A375-(E-Mail Removed)...
> Is there/What is the best way to track expenses in Project Pro/Project
> Server?
>
> I am planning on exporting data out of Project into my financial package &
> would love to suck any expenses (parking, food, lodging, etc) one might
> occur
> on a project as well as the hours spent.
>
> Thank you.
>
> Regards,
> Diane


 
Reply With Quote
 
Diane
Guest
Posts: n/a
 
      05-17-2005, 11:49 AM
Thank you.

"Steve House [Project MVP]" wrote:

> Some of theose expenses can be entered as fixed costs while others like per
> diem might better be tracked as material resources. If you drive to a site
> and are there 3 days you might show a fixed cost of $120 ($20 parking plus
> $100 gas) while there's a 3 day assignment of the per diem that is shown in
> the resource sheet as a material resource with a $75 per day standard rate.
>
> --
> Steve House [MVP]
> MS Project Trainer & Consultant
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
> "Diane" <(E-Mail Removed)> wrote in message
> news:FC7236B6-4E69-4904-A375-(E-Mail Removed)...
> > Is there/What is the best way to track expenses in Project Pro/Project
> > Server?
> >
> > I am planning on exporting data out of Project into my financial package &
> > would love to suck any expenses (parking, food, lodging, etc) one might
> > occur
> > on a project as well as the hours spent.
> >
> > Thank you.
> >
> > Regards,
> > Diane

>
>

 
Reply With Quote
 
 
 
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
How do i track tasks that... DerekM Project Newsgroup 3 05-13-2005 01:26 PM
Tracking travel expenses Ken Project Newsgroup 1 10-17-2004 08:57 AM
how can i keep track of change ? Saba Project Newsgroup 1 09-16-2004 06:00 PM
Re: What's the best way to track progress? Jan De Messemaeker Project Newsgroup 1 07-14-2004 01:00 PM
Re: What's the best way to track progress? Mark Durrenberger Project Newsgroup 1 07-13-2004 05:00 PM



All times are GMT. The time now is 05:08 PM.
Microsoft Office Forums is not affiliated with Microsoft Corporation.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92