Laura
I must be doing something wrong. I have linked three subtasks (lines
2,3,4)together under one task (line 1). Subtask 3 is dependent on the
completion of subtask 2, subtask 4 is dependent on the completion of subtask
3, etc. I checked and the dependencies are set finish to start, with no lag
time. The problem is the dependency is based on the original time estimate
(# of days), rather than the actual finish date (one column "finish" is
driven by duration, while the other column "actual finish" is manually
inserted when a project is actually completed). I want the next phase of the
task to be dependent on the "actual finish" of the project before it. Can
someone help?
2,3,4)together under one task (line 1). Subtask 3 is dependent on the
completion of subtask 2, subtask 4 is dependent on the completion of subtask
3, etc. I checked and the dependencies are set finish to start, with no lag
time. The problem is the dependency is based on the original time estimate
(# of days), rather than the actual finish date (one column "finish" is
driven by duration, while the other column "actual finish" is manually
inserted when a project is actually completed). I want the next phase of the
task to be dependent on the "actual finish" of the project before it. Can
someone help?