I have 3 plans Plan A, B and C. All plans consists of many tasks. I want to view only specific tasks from these plans and not all tasks as when you link the various plans into one plan

Is this possible and if so can someone help

Thank you kindl
 
J

Jack D.

Rukus said:
I have 3 plans Plan A, B and C. All plans consists of many tasks. I want
to view only specific tasks from these plans and not all tasks as when
you link the various plans into one plan.

Is this possible and if so can someone help.

Thank you kindly


Go to insert menu and select column.
Pick one of the flag fields (Flag1 for example)
In that field for the tasks you want to show change the value to Yes.
Now from the project menu select filtered for, then more filters and then
new filter.
Name it what you like.
In the criteria enter Flag1 equals yes (in the appropriate columns)
Then click apply.
All but the flagged tasks will be hidden.


--
Please try to keep replies in this group. I do check e-mail, but only
infrequently.
For Macros and other things check http://masamiki.com/project

-Jack Dahlgren, Project MVP
email: J -at- eM Vee Pee S dot COM


+++++++++++++++++++
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top