Rod,
I appreciate our response. I'm sure you guys go crazy with all of these
questions from the different users
On your first paragraph you mention there would be confusion when you enter
1d from one project to another. I totally agree with that. However, if you
define the hrs/day at the Calendar not Project level, then you just need to
look at Calendar you're using for that task and easily know how many hours
you're getting by entering 1d (8h, 10, 24, etc)
On the Engineering vs. Construction hours, Engineering is not a problem
because they always work 8 hour days. Construction's however are not always
the same. Their default standard work is also 8 hour days, but many times and
because of Construction deadlines they need to speed up certain tasks and
work 5-10s, 6-10s or even 7-10s. Since I'm using role base resources, I don't
want to mess with their resource calendar in the resource sheet. Instead, i
want to be able to dictate their hours by assigning the right Calendar to the
appropriate Task.
I hope I'm making some sense
"Rod Gill" wrote:
> I think you would hate the alternative even more! When I type 1d into a
> duration or work column I want to know exactly how many hours that is. If
> it's 8h in 1 project and 10 in another, very quickly I would have a quagmire
> of misinformation. Okay if I'm only working on 1 project and no one else who
> is using my schedule is viewing any other project: no confusion.
>
> Create 1 base calendar called Engineering Staff and one called Construction
> staff. In the Resource sheet assign the appropriate calendar to each
> resource in the base calendar column. Now at least each resource gets the
> right hours of work time each day.
>
> The day/hour conversion rate should be a fixed value for every project in
> the organisation. I hope that will never change.
>
> --
>
> Rod Gill
> Microsoft MVP for Project - http://www.project-systems.co.nz
>
> Author of the only book on Project VBA, see: http://www.projectvbabook.com
>
>
>
>
> "Hadi" <(E-Mail Removed)> wrote in message
> news:0377CF31-A43B-400E-BD3B-(E-Mail Removed)...
> > Experts,
> >
> > This is more of a comment that a question and I know this has been
> > discussed
> > on this forum many times. I don't understand why Project (2007 or 2010)
> > wont
> > allow us to define hours per day for each calendar rather than using the
> > Tools-->Options-->Calendar to use on all Calendars. I understand that it's
> > only a conversion factor but still. My schedules have Engineering and
> > Construction tasks. for Engineering tasks, I'm using the standard 8-5
> > calendar. So when I punch in 1 day for the duration i want MS Project to
> > show
> > me 8-5 which what it shows me now. Construction tasks however use 5-10's
> > work
> > schedule (8am-7pm) with 1 hr lunch. So, when I punch in 1 day for those
> > tasks
> > I'd like Project to show 8-7 not 8-5. Nor I want to use a 1.25d to get it
> > to
> > show the 8-7. I don't see why any Project needs to have a universal
> > definition of a "day". I really hate this
> >
> > Thanks
> >
> > Hadi
> >
> > __________ Information from ESET Smart Security, version of virus
> > signature database 4930 (20100309) __________
> >
> > The message was checked by ESET Smart Security.
> >
> > http://www.eset.com
> >
> >
> >
>
> __________ Information from ESET Smart Security, version of virus signature database 4930 (20100309) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
>
> .
>