E
ecipm
I see related topics and dialog on this forum, but none that specifically
help with this issue:
Resource A has 2 tasks and works on Task A part-time (let's say a support
function). So, I allocated this resource to 25% to Task A. The other task
has this resource allocated full-time. I expected MSP to "fill-in" the 75%
gap from Task A and have this resource start Task B at the same time as Task
A. But, the resource is actually under-allocated until Task A is complete,
then the resource starts on Task B. The only way I get around this manually
changing the allocation of the concurrent tasks to total 100% (Task A=25%,
Task B=75%). This is very tedious (I have a huge MSP file) and if priorities
change, some of the 'fill-in" tasks may change that need the partial
percentages. Is there an option that enable MSP to fill in the gap
(100%-25%)automatically?
help with this issue:
Resource A has 2 tasks and works on Task A part-time (let's say a support
function). So, I allocated this resource to 25% to Task A. The other task
has this resource allocated full-time. I expected MSP to "fill-in" the 75%
gap from Task A and have this resource start Task B at the same time as Task
A. But, the resource is actually under-allocated until Task A is complete,
then the resource starts on Task B. The only way I get around this manually
changing the allocation of the concurrent tasks to total 100% (Task A=25%,
Task B=75%). This is very tedious (I have a huge MSP file) and if priorities
change, some of the 'fill-in" tasks may change that need the partial
percentages. Is there an option that enable MSP to fill in the gap
(100%-25%)automatically?