P
PJH
I have searched for this problem in this discussion group and have found two
previous entires where resources had been assigned to summary tasks causing
the problem.
However, in my affected plans I do not have any resources assigned. I have
triple-checked that every single task and milestone is updated to 100% but
some summary tasks stay at 99%. I have even made them all 0% and worked my
way through each task individually. I have tried changing the overall project
summary task to 100% and it flicks straight back to 99%. Some of the
summaries stay at 100% until I update somewhere else, then it flicks back to
99% I do not have any links to external tasks.
What else can it be?
Yours Frustratedly.
previous entires where resources had been assigned to summary tasks causing
the problem.
However, in my affected plans I do not have any resources assigned. I have
triple-checked that every single task and milestone is updated to 100% but
some summary tasks stay at 99%. I have even made them all 0% and worked my
way through each task individually. I have tried changing the overall project
summary task to 100% and it flicks straight back to 99%. Some of the
summaries stay at 100% until I update somewhere else, then it flicks back to
99% I do not have any links to external tasks.
What else can it be?
Yours Frustratedly.