N
Nat
Hi,
We are trying to put weekly actual hours in Microsoft
Project from our financial system through an import macro
that we`ve created. However, we have the following
problem: our month end date does not match. Ie. the end
of the month in our financial system could be March 18th
and in MSP, the month end date is March 31st. Is there a
way to change this in MSP? (Also, our month end dates are
never the same from month to month). The results of this
problem is that our actuals at the end of the month never
match between MSP and our financial system.
Help?
Thanks!
Nat
We are trying to put weekly actual hours in Microsoft
Project from our financial system through an import macro
that we`ve created. However, we have the following
problem: our month end date does not match. Ie. the end
of the month in our financial system could be March 18th
and in MSP, the month end date is March 31st. Is there a
way to change this in MSP? (Also, our month end dates are
never the same from month to month). The results of this
problem is that our actuals at the end of the month never
match between MSP and our financial system.
Help?
Thanks!
Nat