Is there a way in regular MS Project or MS Project server to lock actual
hours so they can not be manipulated?
 
G

Gérard Ducouret

Hello,
In Project Server, there is the Managed Periods feature which do that.
Gérard Ducouret
 
T

txtoto

Thank you very much for your help!

Gérard Ducouret said:
Hello,
In Project Server, there is the Managed Periods feature which do that.
Gérard Ducouret
 
J

Jim Aksel

Additionally, in MS Project you can use Tools/Options. Pull the Calculation
tab and then de-select the check box "Actual Costs are always calculated by
MS Project"

Jim
 