P
Pierre M
On an existing project I added a new task in the following manner in the task
details form:
1 entered task name
2 entered duration
3 selected 'fixed duration' in task type
4 selected 'as soon as possible' in constraint
5 selected a predecessor (with a finish date well beyond today or the
project start date
MS Project shows new task starting on the project start date, not FS to the
predecessor as expected... HELP
details form:
1 entered task name
2 entered duration
3 selected 'fixed duration' in task type
4 selected 'as soon as possible' in constraint
5 selected a predecessor (with a finish date well beyond today or the
project start date
MS Project shows new task starting on the project start date, not FS to the
predecessor as expected... HELP