Adding -ONLY- costs to baseline

  • Thread starter Sebastian Cordoba
  • Start date
S

Sebastian Cordoba

Hi guys.

I need to know if it's possible to add ONLY the costs of my project to a
previous saved baseline (that doesn't include them). I'm asking this because
dates have changed and If I set baseline again, I'm losing the previous dates.

Do I need a macro? Any idea for the code?

Thanks for your help.
 
J

Jim Aksel

Hand key it. The problem is it will not timephase unless you break it down
to that detail.

Also, check your rollups to be sure it rolls up for you
--
If this post was helpful, please consider rating it.

Jim

Check out my new blog for more information:
http://www.msprojectblog.com
 
S

Sebastian Cordoba

Thanks Jim.

It sounds pretty obvious but I hadn't even thought about it. It worked!

Bye.
 