Sebastian Cordoba
Hi guys.
I need to know if it's possible to add ONLY the costs of my project to a
previous saved baseline (that doesn't include them). I'm asking this because
dates have changed and If I set baseline again, I'm losing the previous dates.
Do I need a macro? Any idea for the code?
Thanks for your help.