Forums
New posts
Search forums
Members
Current visitors
Log in
Register
What's new
Search
Search
Search titles only
By:
New posts
Search forums
Menu
Log in
Register
Install the app
Install
Forums
Archive
Newsgroup Archive
Project Newsgroups
Project General
Additional time zones in Project
JavaScript is disabled. For a better experience, please enable JavaScript in your browser before proceeding.
You are using an out of date browser. It may not display this or other websites correctly.
You should upgrade or use an
alternative browser
.
Reply to thread
Message
[QUOTE="Gérard Ducouret, post: 159452"] Hello Christina, MS Project can manage several calendars with different times. But it can't manage time zones directly. Nevertheless, you can use some calculated fields (Date1 or Date2 for ex) to do that. Gérard Ducouret [/QUOTE]