M
mankoni
First a statement of my understanding
There are 2 resource attributes with respect units
Max Units - Entered in Resource Sheet and is SET at the RESOURCE Level
Assignment Units - Entered for a given resource BUT at task level.
If the above stmts are correct here is my question.
I have resource R1 set at max units = 50% in the resource sheet. R1 is
not a part time employee so I do not want to mess with the calendar. R1
works on Projects P1 & P2 and hence the 50%.
I have R1 assigned to tasks T1 in Proj P1. At the task level in the
Task Form I specify units = 50%. Work = 8 hrs . Resource = R1. I expect
the DURATION to be calculated as
duration = 8 hrs / 2 hrs = 4 days
The 2 hrs is calculated as --- 50 % * 8 hrs = 4 hrs/ day based on max
units of 50 %
50 % of 4 hrs = 2 hrs / day for Task T1 based on assignment unit of 50
%
Am I right to expect a 4 day task duration ?
There are 2 resource attributes with respect units
Max Units - Entered in Resource Sheet and is SET at the RESOURCE Level
Assignment Units - Entered for a given resource BUT at task level.
If the above stmts are correct here is my question.
I have resource R1 set at max units = 50% in the resource sheet. R1 is
not a part time employee so I do not want to mess with the calendar. R1
works on Projects P1 & P2 and hence the 50%.
I have R1 assigned to tasks T1 in Proj P1. At the task level in the
Task Form I specify units = 50%. Work = 8 hrs . Resource = R1. I expect
the DURATION to be calculated as
duration = 8 hrs / 2 hrs = 4 days
The 2 hrs is calculated as --- 50 % * 8 hrs = 4 hrs/ day based on max
units of 50 %
50 % of 4 hrs = 2 hrs / day for Task T1 based on assignment unit of 50
%
Am I right to expect a 4 day task duration ?