as late as possible constraint


J

jimheike

Hi
When i apply a 'as late as possible' constraint the free float within the
task is used ( as expected) but the total float is also used ie the
subsequent tasks also appear as late as possible.

is there a way to apply the 'as late as possible' constraint without
affecting the free float of subsequent tasks??????

Thanks for your time
regards
James
 
Ad

Advertisements

Ad

Advertisements

D

DavidC

Hi,

Quick thought. Try setting the task that you want to start as late as
possible to be SF successors. So a predecessor task is actually linked as a
successor task but as SF. This sets the start of the task as late as
possible without affecting subsequent tasks and their free float.

Hope this helps

Regards

DavidC
 