C
Cajun007
How do I assign man hours to each task in my schedule?
Task are listed as Fixed Duration and I unchecked Effort Driven. Added
resource to represent crew of 4. Task is twenty days. Now how do I enter
Manhours for this task?
Task are listed as Fixed Duration and I unchecked Effort Driven. Added
resource to represent crew of 4. Task is twenty days. Now how do I enter
Manhours for this task?