I've been asked this more than once recently. We have over 100 employees and
over 3000 tasks in this schedule. It goes to 2010. There are instances
when an employee is working on a long-term task and has to go to a meeting,
or a week long exercise here and there. Is there any way to tell Project to
put a resource on a task all the time EXCEPT when another task is assigned
for that day/week/month? It would seem you could level that one task to
1000, and all the others higher, but leveling never seems to work like I
think it's going to. We want to show our resource is 100% leveled. The
long-term task doesn't really have a specific number of hours - it's just
general support. I was hoping for a non-manual-moving-hours-week-by-week
solution to have Project automatically subtract any additional task hours
from the main Support task. Thanks for your help!
over 3000 tasks in this schedule. It goes to 2010. There are instances
when an employee is working on a long-term task and has to go to a meeting,
or a week long exercise here and there. Is there any way to tell Project to
put a resource on a task all the time EXCEPT when another task is assigned
for that day/week/month? It would seem you could level that one task to
1000, and all the others higher, but leveling never seems to work like I
think it's going to. We want to show our resource is 100% leveled. The
long-term task doesn't really have a specific number of hours - it's just
general support. I was hoping for a non-manual-moving-hours-week-by-week
solution to have Project automatically subtract any additional task hours
from the main Support task. Thanks for your help!