G
GTS
I'm new to Project and have a basic question.
I have two crews available for a series of 8 tasks. I assigned Crew 1 to 4
tasks and Crew 2 to the other 4 tasks.
Here's the question: Crew 1 finishes the 4 tasks several days earlier than
Crew 2. I'd like Crew 1 to help Crew 2 on the last task after Crew 1 is
finished.
BUT, when I assign both crews to that last task it overallocates Crew 1 and
doesn't change the duration. I tried to apply leveling and it makes the
duration longer.
How can I let it know that I want Crew 1 to help Crew 2 on that last task?
It seems straightforward and I can't figure it out!
I have two crews available for a series of 8 tasks. I assigned Crew 1 to 4
tasks and Crew 2 to the other 4 tasks.
Here's the question: Crew 1 finishes the 4 tasks several days earlier than
Crew 2. I'd like Crew 1 to help Crew 2 on the last task after Crew 1 is
finished.
BUT, when I assign both crews to that last task it overallocates Crew 1 and
doesn't change the duration. I tried to apply leveling and it makes the
duration longer.
How can I let it know that I want Crew 1 to help Crew 2 on that last task?
It seems straightforward and I can't figure it out!