Bar Types & Legend

J

Judy

I am having a problem with the way my tracking gantt chart displays. I update
my customer once a month and I want it to display the same everytime, but for
some reason this month it is displaying different information and I can't
figure out how to change it. (I am definately in tracking gantt view each
time).
I want basline milestones to display, but not baseline summary bars. I also
want the Progress summary bars to dispay - hatched bars - but they are gone
and I can't get them back.

In Print Preview
In the legend last month the bars I had were:

critical
critical split
critical progress

column 2
task
split
task progress

Column 3
baseline
baseline split
baseline milestone

Column 4
milestone
summary progress - (Really want this!!)
summary

Column 5
Project summpary
external tasks
external milestone.

Column 6
Deadline


This month something has changed in Project and my legend reads:

Column1
Task
Task Progress
Critcal Task
Critical Task progress

Column 2
Baseline
milestone
baseline milestone
Summary

Column 3 (I don't want any of these)
Rolled up Task
Rolled Up Critical Task
Rolled up Mileston
Baseline Summary (I really don't like this one)

Column 4
Rolled up baseline
Rolled up Baseline milestone
Rolled up progress
split

Column 5
External tasks
Project summary
Group by summary
Deadline
 
G

Gérard Ducouret

Judy,

Aren't you using Project Server ?
If so, the administrator may have changed (by mistake) the Tracking Gantt
view on the server ...

Gérard Ducouret
 
J

JulieS

Hi Judy,

I hope you are able to find my reply to you today. Sorry for the delay.

Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top