Baseline date

J

John

Oren,
If you meant to say, ". . . the 1st date . . ." then you can see it but
only if you are using Project 2003 (I'm not sure if Project 2002 has
this feature but earlier versions do not) by going to
Tools/Tracking/Save Baseline. If any of the 10 available baselines was
previously saved, a date will appear next to that baseline.

Hope this helps.
John
 
O

Oren

John,

Thanks for your answer.
The problem is that I am updating the baseline from time to time (when new tasks are added). The baseline date I see is the latest date when I updated the baseline. I am looking for the original date when I first saved the baseline.
We use Project Server 2003, can i see it?
Thanks,
Oren
 
J

John

Oren,
I don't have Project 2003 server but I doubt it will give the
information you want particularly if you are updating the same baseline.
Since Project 2003 has multiple baselines, I suggest you save each
update as a separate baseline, then you will have each date saved.

If you need more than 10 baselines, I suggest you either set up a custom
field to track baseline dates either manually or automated with a macro,
or perhaps use an Excel spreadsheet to track the baseline date data.

Hope this helps.
John
 