A
Anthropocentric
Microsoft Project is driving me crazy - please help.
I would like to setup MS Project for tracking time for our Software
Development Projects. This is what I want:
- I want to assign tasks to developers
- I want them to know which tasks are assigned to them.
- I want to estimate the time for each task and set this estimate in
stone.
- I want the developers to track their time on each task on a daily
basis.
For example, on monday, they worked on TaskA, 4 hours. Task B, 4
hours.
- I want them to tell me when they are done with a particular task.
- I want to see that they worked MORE or LESS than the original
estimate.
- I want to print a report at the end of each week that shows:
All of our active projects
Who worked on these projects
How many hours they worked on these projects on SUN MON TUE WED THUR
FRI SAT
THAT'S IT!!!
How do I do this!?
Here is what I tried:
We have a Project Server, Sharepoint, etc.
I open up the MS Project Fat Client and I follow the very nice wizard.
I create a project, tasks, assign resources from the server, etc. I
have time tracking set to: "Hours of work done per day or per week"
The tasks I create are effort driven. I set the duration for "4
days". I assign myself as the resources for the tasks.
I create a baseline.
I publish everything to Project Server.
I go to Project Web Access. I click on "Tasks" to see the Timesheet
view. I see that I can edit the "Remaining Work" field and the
"Actual work" for each day.
Everything is very, very confusing from here. Project Web Access
automatically "checks off" the task as complete when the developer
exceeds the time estimate. Sometimes Project automatically adjusts
the "Work" field. All of a suddent the Fat Client pops up and shows
some information that makes no sense...
I want to make this as simple as possible. I want to remove
unecessary, confusing fields and features.
BOTTOM LINE:
What are the settings I need?
On the fat client:
- What columns should I show on the "Gant Chart" View?
- What columns should I show on the "Task usage" View?
- What columns should I show on the "Tracking Gantt" View?
On Project Web Access:
- What columns should I show on the "Timesheet" View?
- What columns should I show on the "Gantt Chart" View?
- What columns should I show on the "Updates" View?
- What columns should I show on the "Project Center"
Is there a set of Views I can just download and install? This
application is crazy. We are a standard software development shop.
Why is this so difficult?
I would like to setup MS Project for tracking time for our Software
Development Projects. This is what I want:
- I want to assign tasks to developers
- I want them to know which tasks are assigned to them.
- I want to estimate the time for each task and set this estimate in
stone.
- I want the developers to track their time on each task on a daily
basis.
For example, on monday, they worked on TaskA, 4 hours. Task B, 4
hours.
- I want them to tell me when they are done with a particular task.
- I want to see that they worked MORE or LESS than the original
estimate.
- I want to print a report at the end of each week that shows:
All of our active projects
Who worked on these projects
How many hours they worked on these projects on SUN MON TUE WED THUR
FRI SAT
THAT'S IT!!!
How do I do this!?
Here is what I tried:
We have a Project Server, Sharepoint, etc.
I open up the MS Project Fat Client and I follow the very nice wizard.
I create a project, tasks, assign resources from the server, etc. I
have time tracking set to: "Hours of work done per day or per week"
The tasks I create are effort driven. I set the duration for "4
days". I assign myself as the resources for the tasks.
I create a baseline.
I publish everything to Project Server.
I go to Project Web Access. I click on "Tasks" to see the Timesheet
view. I see that I can edit the "Remaining Work" field and the
"Actual work" for each day.
Everything is very, very confusing from here. Project Web Access
automatically "checks off" the task as complete when the developer
exceeds the time estimate. Sometimes Project automatically adjusts
the "Work" field. All of a suddent the Fat Client pops up and shows
some information that makes no sense...
I want to make this as simple as possible. I want to remove
unecessary, confusing fields and features.
BOTTOM LINE:
What are the settings I need?
On the fat client:
- What columns should I show on the "Gant Chart" View?
- What columns should I show on the "Task usage" View?
- What columns should I show on the "Tracking Gantt" View?
On Project Web Access:
- What columns should I show on the "Timesheet" View?
- What columns should I show on the "Gantt Chart" View?
- What columns should I show on the "Updates" View?
- What columns should I show on the "Project Center"
Is there a set of Views I can just download and install? This
application is crazy. We are a standard software development shop.
Why is this so difficult?