break in the task sequencing

S

s conklin

I am running Project 2003 standard and I have a break in the task sequencing
it jumps from Task 12 to Task 21. Need to re-establish sequencing 13, 14,
15…21.
i am not sure how this happens, can I get it back to sequential order?
Thanks-
 
J

JulieS

Hello S Conklin,

There could be a couple of things going on:

Tasks have been temporarily hidden by the application of a filter. To
remove any possible filters, press the F3 key on your keyboard.

You have sorted the project and tasks 13 - 20 are mixed in with other
tasks. To re-establish the normal ID order, choose Project Sort > Sort
By > ID.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
S

s conklin

Julie, the F3 trick worked, I will try the other solutions for the other
question you answered in a bit, thanks again
1
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top