calculate duration

S

sulvador

Hi!

I'm exporting data from another program (PROGA) into the MSP database.
In PROGA only the start and end date of a task are known. I would like
to insert the date from PROGA to the MSP databse and let MSP calculate
the duration.

WHen I try to do this MSP calculates the duration as 1 day??? It reads
the duration (which is 0)...

so... How can I 'tell' MSP to calculate the duration from the start
and end date

thanks in advance,
Rick Oosterholt
 
J

John

Rick,
Why are you asking the same question again? Jan gave you an answer in
your first post (i.e. set up a custom field with a formula).

John
 