How can I make MS Project use "Baseline 1 Finish" or "Baseline 2 Finish"
dates instead of "Baseline Finish" for calculating the Finish Variance?
I need to track dynamic projects whos finish dates keep changing every week,
so I want the Finish Variance to show the value based on the last baseline
(which could be baseline 1 finish, baseline 2 finish, baseline 3 finish, etc).
Thanks in advance