Calculate finish variance using Baseline 1 Finish or Baseline 2 Fi

W

wasaan

Greetings,
How can I make MS Project use "Baseline 1 Finish" or "Baseline 2 Finish"
dates instead of "Baseline Finish" for calculating the Finish Variance?
I need to track dynamic projects whos finish dates keep changing every week,
so I want the Finish Variance to show the value based on the last baseline
(which could be baseline 1 finish, baseline 2 finish, baseline 3 finish, etc).

Thanks in advance
 
G

Gérard Ducouret

Hello wasaan,

Tools / Options / Calculation / Earned value / Baseline for Earned Value
calculation... (or something like that : I don't have the English version in
front of me)
Hope this helps,

Gérard Ducouret
 
W

wasaan

Thanks Gerard. I will try that. Thanks again

Gérard Ducouret said:
Hello wasaan,

Tools / Options / Calculation / Earned value / Baseline for Earned Value
calculation... (or something like that : I don't have the English version in
front of me)
Hope this helps,

Gérard Ducouret
 