jlg
My colleague and I are trying the same entry in MS Project and are
getting different results:
On my PC, I enter:
task 1 is 2 days duration
task 2 is 3 days duration
task 3 is 4 days duration.
I then enter resource1 to task 1. Project shows task 1 starting 28June.
I then enter resource1 to task 2. Project shows task 2 starting 30June.
I then enter resource1 to task 3. Project shows task 3 starting 5July.
my colleague does exact same steps.
his Project tells him all 3 tasks start on 28June.
I have searched this user group - and found the entries from last
summer - all of which we have tried (ensuring automatic calculation is
on, verifying constraints are asap, verifying no constraint dates, no
predecessors, calendars are set identically to work a 6.5 hr day, no
start date or end dates are entered, etc., etc.)
any other ideas? thx...
getting different results:
On my PC, I enter:
task 1 is 2 days duration
task 2 is 3 days duration
task 3 is 4 days duration.
I then enter resource1 to task 1. Project shows task 1 starting 28June.
I then enter resource1 to task 2. Project shows task 2 starting 30June.
I then enter resource1 to task 3. Project shows task 3 starting 5July.
my colleague does exact same steps.
his Project tells him all 3 tasks start on 28June.
I have searched this user group - and found the entries from last
summer - all of which we have tried (ensuring automatic calculation is
on, verifying constraints are asap, verifying no constraint dates, no
predecessors, calendars are set identically to work a 6.5 hr day, no
start date or end dates are entered, etc., etc.)
any other ideas? thx...