ESPitts said:
I've got a customer who wants to see the duration in calendar days. Is there
a way to change the Duration column such that it shows calendar instead of
business days? Even if I build it normally and then change the view that
would be okay.
ESPitts,
Yes. There is a utility macro called Format Duration but it does not do
exactly what you want. A variation of that VBA code could be created to
translate the Duration field for you however if you do not have VBA
experience, that doesn't help much. There is another method though that
should work.
Set up a custom field (e.g. Duration1). Put the following formula in the
field:
DateDiff("d",[Start],[Finish])*480+480
I suggest you simply have the customer view the custom field as the
duration but with a little more effort the Duration field itself could
be converted. Note: simply copying the custom field over to the Duration
field will not work.
John
Project MVP