S
Shaun
In my Project, my tasks have different resources from different departments.
Some of these resources want to change their baseline hours because of an
increase in scope. How do I change the baseline hours for 1 resource in a
task but leave the original baseline for the other resources? When I click
save baseline for the selected task, the baselines for all of the resources
change to the amount of work for the resources. Some of the resources have
been able to complete their portion of the task in less time than was
originally baslined and I want to be able to show this varience. Also how do
I get the Summary tasks of not only the sub set but the top levels to show
the increase?
Some of these resources want to change their baseline hours because of an
increase in scope. How do I change the baseline hours for 1 resource in a
task but leave the original baseline for the other resources? When I click
save baseline for the selected task, the baselines for all of the resources
change to the amount of work for the resources. Some of the resources have
been able to complete their portion of the task in less time than was
originally baslined and I want to be able to show this varience. Also how do
I get the Summary tasks of not only the sub set but the top levels to show
the increase?