colin919 said:
Is it possible to back load (or bell curve load) a resource, without project
auto-leveling?
Would like to schedule 850 hours of work, across 23 days, with an 8 man
crew. Can get project to accept the work, and crew size, but it will not keep
the date range.
Is there another program that can accomplish this if project cannot?
colin919,
The only reason Project auto-levels is because the option for
auto-leveling has been enabled - so turn it off (Tools/Level Resources).
There are several contours that can be applied to Work. Any one of them
can either be applied to a resource's assignment or all work performed
by one or more resources. I suggest you add the Work Contour field to
the Task Usage view and then click on the "help on work contour" item
when you hover the mouse over the Work Contour column heading.
With regard to the 850 hour work effort task, you probably need to make
the task Fixed Duration, non-effort driven (Project/Task
Information/advanced tab). Then set the Duration for 23 days, give it a
Work value of 850 hours and assign the 8 man crew, (which I assume is a
group resource rather than 8 individual names). Doing so will result in
the 8 man crew with an assignment level of a little less than half time.
Hey man there nothing that Project can't do (?)
John
Project MVP