D
Dena
I'm having trouble getting Project to properly update my start and finish
dates when I set a task to 100% complete. I've set up my gantt chart view to
show columns for percent complete and actual finish dates. In my Project
training course, I was told that if I set a task to 100% complete, Project
would automatically assume today's date as the actual finish date, but this
is not happening. Instead the actual finish date is being recorded as the
regular finish date that was first estimated. I want it to automatically
record the current calendar date as the actual finish date when I set a task
to 100% complete.
I also want the start date of the task that is being set to 100% complete to
remain fixed, and the duration to adjust accordingly. THEN I want the start
dates of all subsequent linked tasks to update based on the actual finish
date of the predecessor.
Can someone help me with this? If this is not possible with Project as it
comes, perhaps there is a script that can do this?
dates when I set a task to 100% complete. I've set up my gantt chart view to
show columns for percent complete and actual finish dates. In my Project
training course, I was told that if I set a task to 100% complete, Project
would automatically assume today's date as the actual finish date, but this
is not happening. Instead the actual finish date is being recorded as the
regular finish date that was first estimated. I want it to automatically
record the current calendar date as the actual finish date when I set a task
to 100% complete.
I also want the start date of the task that is being set to 100% complete to
remain fixed, and the duration to adjust accordingly. THEN I want the start
dates of all subsequent linked tasks to update based on the actual finish
date of the predecessor.
Can someone help me with this? If this is not possible with Project as it
comes, perhaps there is a script that can do this?