Hi,
Scenario:
I have to create a milestone in my schedule in a future date, however this
task does not a processors and setting a date manually creates a constraint
for the milestone.
-My Question is:
How can I create a task without adding constraint ?
What is the preferred approach for creating milestone in a future date?