control the priority of tasks for the tasks assigned to one resour

D

DDDDDD

I have a question related to the recourses and task dependency.
If I have the following task
Tasks Predecessor Resource
TaskA Res1
TaskA.1 TaskA Res2
TaskA.2 TaskA.2 Res1
TaskB TaskA Res1
TaskB.1 TaskB Res2
TaskB.2 TaskB.1 Res1
TaskX.1 TaskX Res1
So, I need Res1 to start in taskB before taskx.1 but the MS schedule is
starting in taskX.1 after taskA for Res1
So, my question is how can I control the priority of tasks for the tasks
assigned to a certain(one) resource?
 
J

Jan De Messemaeker

Hi,

Insert the priority field, set priorities (1-1000) and in Tools, Resource
leveling, change the order to Priority, Standard.
HTH
 
D

DDDDDD

it didn't work,i just need something to say to the schedule just moveup this
task as this taskb is more important than taskx.1.
 
D

DDDDDD

yes, i do leveling.
i changed the priority field to 700 for taskb and keep taskx.1 500 and
performed leveling as you mentioned.
but dates didn't change.
then i tried to put the priority field to 300 for taskb and keep taskx.1 500
and performed leveling as you mentioned.
but dates didn't change.
 
J

Jan De Messemaeker

Hi,

I did exactlty that and leveling gives me the sequence A, B, B2, A2, X1 for
R1.
You don't have any summary tasks do you? I mean, A1 and A2 aren't "children"
of A for instance?
 
D

DDDDDD

Thanks alot Jan
i have done another trial.
and it worked thanks again.
i problem now that multiple task are starting in the same time and day for
the same resource, any suggestions.
ddd
 
J

Jan De Messemaeker

You obviously make a mistake, but I cannot see which one from here
Some ideas can be found in FAQ 28 (URL of the FAQs in my signature)
If that doesn't help send me the file (jandemesATprom-ade.be)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top