cost baseline issue

S

SAM

I'm supporting a user running Project 2003. The issue is when saving a
sub-task to the baseline with a cost of $0, the summary task’s baseline cost
will also become $0 even though other sub-tasks have a baseline cost
associated.

The user has tried this on multiple computers always getting the same result
(running the same version of Project).

The user has also emailed the file to someone outside our network for advice
on the issue and it works properly on their computer (running an older
version of Project).

i've currently request the user follow the instructions concerning "File
Bloat? Might be corrupt". Thankyou in advance for any insight on this issue.
 